Portland Avenue Area

GovDelivery envelope logo Opens in new window Subscribe to email updates

Overview

Reconstruction consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map or see below for updates.

September 13, 2019

Landscape repairs are scheduled to start soon and continue the week of September 16, 2019. Raising of manholes and gate valves in the streets are scheduled for the week of September 16, 2019.

September 3, 2019

Sod has been installed. Please refrain from mowing the new sod. The contractor will water and maintain the sod for 30 days.  Please watch for more information to be delivered to your mailbox.